| July | August | September | October | November | December | January | February | March | April | May | June |
| Commencement | |||||||||||
| Foundations | |||||||||||
| Frames | |||||||||||
| Retaining walls | |||||||||||
| First floor Timber frame External walls | |||||||||||
| Concrete ground floor Roof on | |||||||||||
| Lay Sedum Cover Curtain Walling | |||||||||||
| Watertight 1st Fix for M & E | |||||||||||
| Staircase | |||||||||||
| Finishes 2nd Fix M & E | |||||||||||
| Fixtures, Fittings Signage Cleaning Commissioning | |||||||||||
| Handover |